Language
Home> Global Cases> Tanzania 1,200t/d Gold Mineral Processing Plant
Tanzania 1,200t/d Gold Mineral Processing Plant
CASES

Tanzania 1,200t/d Gold Mineral Processing Plant

The Tanzania 1,200t/d gold mineral processing plant was an EPC+M+O project. The ore consisted of sulfide (10.7g/t) and oxide (2.4g/t), with Au being the only valuable element. They achieved a leaching rate of 93.75% and 91.58% respectively through the all-slime cyanidation gold extraction process.

Xinhai Solution

01

All-slime cyanidation process was adopted.

02

Crushing stage: one open-circuit crushing process;

03

Grinding and classification stage: one closed-circuit grinding, cyclone classification process;

04

Separation stage adopted the all-slime cyanidation process was adopted, the gold-bearing carbon entered the desorption electrolysis system to extract gold, smelting gold slime, and the tailings were stacked after the thickening and dewatering.

Main Equipment

Project Result

Tanzania 1,200t/d Gold Mineral Processing Plant

The Tanzania 1,200t/d gold mineral processing plant was an EPC+M+O project. The ore consisted of sulfide (10.7g/t) and oxide (2.4g/t), with Au being the only valuable element. They achieved a leaching rate of 93.75% and 91.58% respectively through the all-slime cyanidation gold extraction process.

Project Site

Tanzania 1,200t/d Gold Mineral Processing Plant
Tanzania 1,200t/d Gold Mineral Processing Plant
Tanzania 1,200t/d Gold Mineral Processing Plant


Mineral Processing
EPC and Equipment

Tel: +8615832885494
E-mail: xhxu@xinhaimining.net
Support: 北京鑫互联科技有限公司

Home About us EPC Products Solutions Cases News Contact Us 3D Exhibition Room
sitemap   © 2014 Shandong Xinhai Mining Technology & Equipment Inc.

Leave Message
contact
Leave Message
contact